Cogent Energy has designed and installed a state of the art cogeneration plant at 101 Miller Street, North Sydney. This building is the largest commercial building in North Sydney and comprises premium office space and retail shops. This is the largest cogeneration plant in a commercial tower in Australia.
- Building Owner:
- Mirvac and Eureka Funds Management
- Location:
- North Sydney
- Building Description:
- Commercial complex – premium offices & retail plaza
- Building Size:
- 40,000 sqm Commercial, 10,000 sqm retail
- Plant Operational Date:
- In operation since 1 November 2008
Cogeneration Configuration

The 101 Miller Street cogeneration plant comprises of 2 x 1,166 kW MTU Series 4000 cogeneration engines that are connected in parallel to the grid. Each engine is coupled to a 750 kW Thermax exhaust absorption chiller. The absorption chillers are fully integrated into the building’s chilled and condenser water systems.
The plant is set up to operate either in grid parallel import or island mode and operates automatically during the peak and shoulder demand periods or during grid outages as emergency backup.
Plant Capacities
- Peak Electrical:
- 2,332 kW at 0.8 power factor
- Peak Cooling:
- 1,500 kW
- Energy Efficiency:
- 70% Thermal Efficiency (estimated)
Benefits
- Reliability:
- Highly reliable cogen solution with grid parallel import
- Energy Efficiency:
- 5 star NABERS and 5 star Green Star
- Backup:
- Emergency Backup provided
- Sustainability:
- Estimated saving of up to 6,000 tonnes of CO2 per annum.